Developer |
Sikles Hydro Power Pvt.Ltd |
Project |
Madkyu Khola Hydropower Project |
District |
Kaski |
Location of Project Site |
Todi and Parhche VDC |
Water Source |
Madkyu Khola |
Type of Scheme |
RoR |
Access Road |
36 Km upto Sikles Village, 12 Km from sikles village to power House and 4 Km power house to Head works site. |
Installed Capacity |
13000 kW |
Gross head |
1485 m |
Design Discharge |
3.71 m3/s |
Catchment Area at Intake |
71.3Km² |
Head works |
Stone lined free flow weir 18m |
Weir Crest Elevation |
EL 1738m |
Under sluice length |
3m |
Intake Type |
Side Intake with coarse rack |
Connecting Tunnel to pipe desander |
95m and 2.0 diameter |
Headrace Canal |
1.45m |
Desander |
Underground and Rectangular with single basin. |
Penstock Pipe |
Exposed Steel Pipe |
Length |
660 m |
Powerhouse |
Surface (30.6m *18.9m*10.7m) |
Tailrace |
RCC Rectangular, 30.0m |
Turbine |
Pelton, Horizontal axis, two |
Transmission |
26.35km, 132kV |
Interconnection/Metering Point |
NEA 132 kV at Lekhnath Substation |
Deemed Generation |
58.945.33 GWh |
Construction Started |
2068 Kartik |
COD/Commissioned date |
30 Magh, 2074 Purposed |
Rate per unit of Energy |
Rs 4 on wet season and Rs 7 for dry season for 9968 KW, and Rs 4.80 for wet season and Rs 8.40 for dry season for 3000 Kw. |
Project Cost without IDC |
1 Arba 48 Crore 99 Lakhs |
Annual Revenue |
About 30 Crore 29 Lakhs 83 Thousand 535 |
Total Cost at Commissioning |
2 Arba 17 Crore |
Debt : Equity |
70:30 |
Financed by |
Nepal Bank Limited as Lead Bank, Nepal Bangladesh Bank, Global Ime Bank Limited, Siddhartha Bank Limited, Agricultural Bank Limited, NIDC Development Bank Limited. |